• Thanks for stopping by. Logging in to a registered account will remove all generic ads. Please reach out with any questions or concerns.

Replacing the Subs

Smart move by Japan. I wonder if they decided to duck the GBA freight train and politics of Canadian defence procurement heading their way.
Also they are furiously busy building their own fleet.
GBA is just a way to ensure you considered all sailors in your design. 95th percentile male, 5th percentile female for size so equipment and spaces allow for all people to work there without standing on a stool or always hitting their heads. Heads and wash place considerations. Messing and bunking considerations. GBA in engineering and design makes ships better for the crew.
 
I heard the rumour mill on this as well awhile ago, I was expecting some kind of news given the RFI deadline was relatively recently but didn’t think it would be this openly addressed.
 
I heard the rumour mill on this as well awhile ago, I was expecting some kind of news given the RFI deadline was relatively recently but didn’t think it would be this openly addressed.
Question: when can we expect the first to be delivered once a contract is signed?
 
GBA is just a way to ensure you considered all sailors in your design. 95th percentile male, 5th percentile female for size so equipment and spaces allow for all people to work there without standing on a stool or always hitting their heads. Heads and wash place considerations. Messing and bunking considerations. GBA in engineering and design makes ships better for the crew.
The French Barracuda class was specifically designed for mixed gender crews.
 
Neither France nor Japan (and certainly not Korea) make it a religion that can crater a project like Canada.
 
Back
Top