- Reaction score
- 17,208
- Points
- 1,010
He was in a class of his own, that for certain.
SeaKingTacco said:He was in a class of his own, that for certain.
SeaKingTacco said:There is a lot more to a helicopter than the airframe.
Engines. Gearboxes. Electrical systems. Avionics. Sensors. Safety systems.
All of that needs doing on our Sea Kings.
Colin P said:To date, 11 Cyclones have been delivered to the Royal Canadian Air Force, of which three are operated for testing and evaluation.
jmt18325 said:I get that - but if it's worth it for them to buy, it might have been worth it for us to fix them. I'm not convinced that the CH-148 will ever be delivered at this point.
Chris Pook said:Colin P said:To date, 11 Cyclones have been delivered to the Royal Canadian Air Force, of which three are operated for testing and evaluation.
They have been delivered - sort of - but not really.
suffolkowner said:There's 4 more in the pipe for delivery this year as well.
suffolkowner said:Well block two delivery is supposed to begin in 2018. Block 1.1 delivery will continue as will Sea King removal. If the bugs aren't worked out by 2018 we're going to have a problem
Cyclone helicopters to reach full operating capability in 2025: DND
Long, tortured story of getting replacement for Sea Kings a 'case study' in how not to do it
http://www.cbc.ca/news/politics/cyclone-helicopter-operational-1.3746627
Eye In The Sky said:And that is still a ridiculous (long) timeline. The Cyclone project is a great study of how NOT to procure...well anything.
If you want to read up some on a helicopter project that went well, read up on the NH90 NFH (NATO Frigate Helicopter) project that produced not only MH, but Army TacHel airframes as well.
suffolkowner said:You would prefer the NH90 over the AW101 or Cyclone?
Eye In The Sky said:And that is still a ridiculous (long) timeline. The Cyclone project is a great study of how NOT to procure...well anything.
If you want to read up some on a helicopter project that went well, read up on the NH90 NFH (NATO Frigate Helicopter) project that produced not only MH, but Army TacHel airframes as well.
...The initial prototype took off on its debut flight in 1990 and, in 2007, the first examples were ready for combat....